Peachtree Industrial Flip
Status: in_progress · Phase: framing
Budget
$85,000
Spent
$31,200
Remaining
$53,800
% Complete
37%
Permit
Number: BP-2026-0412
Status: issued
Lender
Sunbelt Lending
Milestone Summary
Total: 4 · Flagged: 0 · Draw-eligible: 2
Milestones
| Phase | Name | Status | Budget | Spent | % Complete | Draw eligible |
|---|---|---|---|---|---|---|
| demo | Demolition + debris haul | verified | $6,500 | $6,500 | 100% | eligible |
| framing | Framing + structural repair | pending_verification | $14,000 | $13,200 | 95% | eligible |
| mep | Rough-in MEP | in_progress | $22,000 | $11,500 | 50% | no |
| finishes | Finish carpentry + paint | pending | $18,000 | $0 | 0% | no |
Photo verification
Upload UI comes post-v1. Photos can be registered via POST /v1/projects/00000000-0000-0000-0000-000000000401/photos with metadata.
Draw Requests
| # | Amount | Status | Blockers |
|---|---|---|---|
| #1 | $20,500 | draft | 0 |